Generator Interconnection Studies

  • CA200S System Impact Study

    System Impact Study (SIS) was finalized on 1-31-2017 and sent to the Interconnection Customer (IC).  EPE conducted the results meeting with IC on 3-1-2017 via conference call.  IC will be performing internal study using the base cases used in the SIS before moving to the Facilities Study phase of the LGIP.