Tuskegee-Pine

Tuskegee to Pine 345 kV Transmission Lines Project

The Project involves the construction of two (2) new 345 kV transmission lines in El Paso County, Texas. The Project will connect Tuskegee Substation and Pine Substation, both located in east El Paso County, Texas. 

 

The proposed transmission lines are required to maintain the reliability of the transmission system in the area.

 

El Paso Electric Company (EPE) filed an application with the Public Utility Commission of Texas (PUCT) to amend its Certificate of Convenience and Necessity (CCN) in order to construct this project under Docket No. 60152.

Project maps available in the links below:

 

Estimated project timeline

Application filing: August 31, 2026.

PUCT Decision: Anticipated in February 2027.

Energize Facilities: Anticipated in May 2030.