Pine-Caliente

Pine to Caliente 345 kV Transmission Line Project

The Project involves the construction of a new 345 kV transmission line in El Paso County, Texas. The Project will connect Pine Substation and Caliente Substation, both located east of El Paso County, Texas. 

The proposed transmission line is required to maintain the reliability of the transmission system in the area.

El Paso Electric Company (EPE) filed an application with the Public Utility Commission of Texas (PUCT) to amend its Certificate of Convenience and Necessity (CCN) in order to construct this project under Docket No. 60016.

Project maps available in the links below:


Estimated project timeline

Application filing: July 30, 2026.

PUCT Decision: Anticipated in January 2027.

Energize Facilities: Anticipated in May 2029.