2021

2020

2019

 EPE Fall 2017 Cluster Restudy #4
 Fall 2017 LGIP Cluster Restudy #3 02-08-19

2018

 Fall 2017 LGIP Cluster Restudy #2 11/05/18

 EC300W ERIS Final Report 10-01-2018
ERIS Final Report for EC500W project (was reduced by Interconnection Customer to 300 MW for ERIS study)

 Fall 2017 Cluster LGIP Restudy 09/20/18

 H252W SIS Restudy 08-2018
H252W ERIS Generator Interconnection Restudy report.

 N200S Solar PV SIS Re-Study Report 08-2018
EPE N200S SIS Restudy Report 8-29-2018

 

2017

 LA450S ERIS Restudy Final Report 11-30-2017
Re-Study of LA450S for Energy Resource Interconnection Service (ERIS)

 LA450S SIS Final Report 6-29-2017
Final NRIS SIS Report for LA450S Project.

 CA200S System Impact Study 1-31-2017
System Impact Study (SIS) was finalized on 1-31-2017 and sent to the Interconnection Customer (IC).

 

2015

 DS90S PV Project
Final Report of the DS90S Solar PV Facilities Study.

 

2014

 115 kV Cluster SIS
System Impact Study Final Report of 115 kV Cluster Study

 

2013

 10 MW Solar PV Facilities Study 08-2013
Facilities Study for 10 MW Solar PV Generation Project

 10 MW Solar PV Generation Feasibility Study 05-2013
Feasibility Study for 10 MW Solar PV Generation Project

 East El Paso Cluster Facilities Study
East El Paso Cluster Facilities Study Report - January 2013

 

2012

 HL20S Facilities Study Report
HL20S Facilities Study Report

 MS50S Facilities Study Report
Facilities Study Report for MS50S Solar PV Interconnection Project

 Addendum to 345 kV Cluster Study
Addendum to 345 kV Cluster Study 08-2012

 Addendum #2 to East El Paso Cluster SIS
Addendum #2 to East El Paso Cluster SIS 08-2012

 Restudy of East El Paso Cluster SIS
Restudy of East El Paso Cluster SIS 08-2012

 Addendum to East El Paso Cluster SIS
Addendum to East El Paso Cluster SIS 07-2012

 East El Paso Cluster System Impact Study Final Report
East El Paso System Impact Study Final Report 06-2012

 HL20S PV Feasibility Study
HL20S PV Feasibility Study 07-2012

 Addendum to RG87G 20 MW Increase SIS
Addendum to RG87G 20 MW Increase SIS 08-2012

 RG87G 20 MW Increase SIS
System Impact Study to increase RG87G gas fired project generating capacity from 87 MW to 107 MW 03-2012

 MS50S ERIS Final Report

 WA300W SIS Re-Study #2 Final Report
SIS Study for WA300W Wind Project

 ART320W ERIS Final Report

 RG87G Facilities Study
Facilities Study for RG87G Generation Interconnection Project

 345 kV Cluster Facilities Study
Facilities Study for 345 kV Cluster Study

 

2011

 RG87G SIS Re-Study
Re-Study of RG87G SIS due to withdrawal of project senior to the RG87G project.

 RG87G SIS
System Impact Study for 87 MW Gas Turbine

 LU99.8S Feasibility Study
Feasibility Study for 99.8 MW Solar PV Project at Luna 345 kV Substation.

 345 kV Cluster SIS Re-Study #2
345 kV Cluster SIS 07- 2011.

 345 kV Cluster SIS Re-Study #1
345 kV Cluster SIS Restudy 05- 2011.

 

2010

 Generator Interconnection Cluster Study-345 kV SIS
345 kV Cluster System Impact Study 11- 2010.

 Generator Interconnection Cluster Study - 345 kV Feasibility
345 kV Cluster Feasibility Study 05- 2010.

 99.8 MW Solar Facilities Study on Diablo-Santa Teresa 115 kV line

 99 MW Wind Park Interconnection Facilities Study-SL 345 kV Line

 Diablo-Santa Teresa 115 kV line - 99.8 MW Solar (SIS Cluster)

 Addendum to 500 MW Wind Amrad-Eddy 345 SIS Final Report_rev1a

 Springerville-Luna 345 kV line-99 MW Wind (SIS)

 Additional Eddy DC Tie Final Report

 Eddy County - 80 MW Generator Appendix A

 Eddy County - 80 MW Generator Appendix B

 Eddy County - 80 MW Generator Appendix C

 Gen Interconn Study - 30 MW (Wind) Sierra Blanca

 Gen Interconn Study - 80 MW at Eddy County 345

 Gen Interconn Study - 99 MW Wind on SL Line

 Gen Interconn Study - 120 MW Solar at Luna 345

 Gen Interconn Study - 130 MW (ST) Afton 345

 Gen Interconn Study - 135 MW (GT) at Afton 345

 Gen Interconn Study - 150 MW (Wind) Coyote

 Gen Interconn Study - 160 MW on Luna-Newman 345

 Gen Interconn Study - 250 MW at Newman 115 or RGD 115

 Gen Interconn Study - 250 MW at WR

 Gen Interconn Study - 285 MW at Caliente

 Gen Interconn Study - 290 MW at Newman 115

 Gen Interconn Study - 300 MW Solar at Luna 345

 Gen Interconn Study - 495 MW (Wind) on EP Line (SIS) Addendum

 Gen Interconn Study - 500 MW (Wind) near Amrad (Phased)

 Gen Interconn Study - 500 MW (Wind) near Amrad (SIS)

 Gen Interconn Study - 500 MW at Newman 115

 Gen Interconn Study - 500 MW at Newman 345

 Gen Interconn Study - 500 MW Wind near Amrad

 Gen Interconn Study - 505 MW at Hidalgo 345

 Gen Interconn Study - 600 MW at Luna 345

 Gen Interconn Study - 990 MW Wind on EP Line

 Gen Interconn Study - 1200 MW at Luna 345

 Gen Interconn Study by TNMP - 310 MW at Hidalgo

 Gen Interconn Study EPE Review - 310 MW at Hidalgo 345

 Interaction Study (GE) - 500 MW Wind near Amrad and Eddy HVDC

 Short Circuit Analysis - 135 MW at Afton 345 addendum

 Short Circuit Analysis - 160 MW on Luna-Newman 345

 Short Circuit Analysis - 225 MW at Afton 345

 Short Circuit Analysis - 250 MW at Newman 115 or RGD 115

 Short Circuit Analysis - 290 MW at Newman 115

 Short Circuit Analysis - 500 MW at Newman 115

 Short Circuit Analysis - 500 MW at Newman 345

 Short Circuit Analysis - 500 MW Wind near Amrad

 Short Circuit Analysis - 505 MW at Hidalgo 345

 Short Circuit Analysis - 600 MW at Luna 345

 Short Circuit Analysis - 1200 MW at Luna 345

 Transmission Changes to the 500 MW Wind Amrad-Eddy 345 SIS Final Report

 Transmission Interconnection Study - 200 MW HVDC at Eddy County

 Transmission Interconnection Study - 660 MW HVDC near Newman 345

 Transmission Upgrade Analysis 10-18-2006 RFP

 Transmission Upgrade Analysis 12-2006 RFP

 

2009

 Re-Study West Mesa-Arroyo 345 kV line-990 MW Wind

 West Mesa-Arroyo 345 kV line-495 MW Wind (SIS)

 

2008

 West Mesa-Arroyo 345 kV line-990 MW Wind